Building construction quality monitoring method, system and device and storage medium
A quality monitoring and building construction technology, applied in the field of devices and storage media, systems, and building construction quality monitoring methods, can solve construction quality problems, uncertainties, affecting the final quality of buildings, etc., so as to facilitate search and improve construction quality. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Example Embodiment
[0065]Example one:
[0066]A construction quality monitoring method, referencefigure 1 ,include:
[0067]101. Obtain construction drawings, perform BIM modeling on the target building according to the construction drawings, and generate construction animations.
[0068]Specifically, construction animation is a 4D simulation, combined with BIM modeling technology to generate process animation. Among them, the construction plan includes the construction plan and the CAD plan drawing of the target building when obtaining the construction drawings. The plan contains a complete construction plan. The construction plan includes at least several construction steps, and the construction time of each construction step is planned, that is, the construction schedule plan.
[0069]First, build a three-dimensional model of the target building structure using Autodesk Revit software based on the CAD plan of the target building. Among them, the three-dimensional model of the building structure includes the build
Example Embodiment
[0114]Example 2:
[0115]Construction quality monitoring system, referencefigure 2 ,include:
[0116]Generating Apparatus 201, acquires construction drawings, perform BIM modeling according to the construction drawings, and generates construction animation.
[0117]The partitioning device 202 divides the construction animation into several parts segments, each of which corresponds to a construction step.
[0118]The monitoring device 203 monitors the construction process of the target building in real time to generate construction video.
[0119]Modeling device 204, according to the construction video 3D modeling, generating construction model.
[0120]The comparison device 205 matches the construction model to the segment corresponding to the construction animation and comparison.
[0121]Further, whenever a construction step is completed, the construction model at this time is labeled;
[0122]The scaled construction model is compared with the fragment corresponding to the construction animation.
[0123]Furth
Example Embodiment
[0134]Example 3:
[0135]Building construction quality monitoring device, referenceimage 3 ,include:
[0136]The generating device 301 acquires the construction drawing, and the target building is used to generate construction animation according to the construction drawing.
[0137]The division device 302 divides the construction animation into several parts segments, each of which corresponds to a construction step.
[0138]The monitoring device 303 monitors the construction of the target building in real time, and generates a construction video.
[0139]Modeling device 304, according to the construction video 3D modeling, generating a construction model.
[0140]The comparison device 305 matches the construction model to the segment corresponding to the construction animation and comparison.
[0141]Further, whenever a construction step is completed, the construction model at this time is labeled;
[0142]The scaled construction model is compared with the fragment corresponding to the construction animatio
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap